| Proj # | Project Name |
| % |
Status
Building Name - Project Description
|
| Active |
Last Updated
Project update
|
| R8278 | Manager:Dave Bonselaar SRC-VARIOUS AREA-PAINT |
Status:Issued to Shop Student Recreation Center - Paint various areas. Repaint court lines on 1st floor gym. | |
Active | Status Updated:13-OCT-09 80% complete. Using for fill in work per Amy Seth's direction. Amy is working on a new list of areas to be painted this week |
| R8667 | Manager:Dave Bonselaar HAE-3431-UPGRADE |
Status:Issued to Shop Haenicke Hall - Install sink, electrial for computers and two hoods | |
Active | Status Updated:11-NOV-09 60% Sink needs to be installed, Material is on order. Electrical work is in process and working on sink specs |
| R8858 | Manager:Dave Bonselaar COE-ASSEMBLE FURNITURE |
Status:Issued to Shop Engineering and Applied Sciences - assemble furniture | |
Active | Status Updated:11-NOV-09 25% Panels have been moved into the space and product is scheduled to be cleaned this week |
| R8885 | Manager:Dave Bonselaar WOOD-3936-RENOVATE SPACE |
Status:Issued to Shop Wood Hall - | |
Active | Status Updated:06-NOV-09 85%Cabinets are installed, Electrical is complete. Painting needs to be completed and well as th plumbing. Installing sink and handles |
| R8895 | Manager:Dave Bonselaar SCH-2350-RECONFIGURE ROOM |
Status:Issued to Shop Schneider Hall - Reconfigure rooms. | |
Active | Status Updated:20-NOV-09 45% Furniture has been ordered. Construction has begun. Carpet in this space is being installed today and over the weekend (Nov 21). Lighting finalaized and approved and ready for order. |
| R8920 | Manager:Dave Bonselaar GIBBS HOUSE-REPLACE BATHROOM FLOORING |
Status:Issued to Shop Gibbs House - Parkview Farm - Replace bathroom flooring. | |
Active | Status Updated:11-NOV-09 30% Additional lead paint has been scraped and painting is in process |
| R8977 | Manager:Dave Bonselaar BC-220-SALP OFFICE |
Status:Issued to Shop Bernhard Center - Build new walls to accomodate offices | |
Active | Status Updated:06-NOV-09 45% Carpenters are building walls and electrical work is in process
Finishing furniture layout tag lists. 3 of 4 furniture orders received to date |
| R7811 | Manager:Dan Brimmer BC-EMERGENCY GENERATOR |
Status:Issued to Shop Bernhard Center - Deferred maint. $125000 | |
Active | Status Updated:16-NOV-09 11% Design Complete, ATS on site, generator to be bid in next month once direction is provided
Submitted for DEQ approval contacted Kalamazoo Elect to install ATS . Transfer switch installed, coordinating outage for connection.
Switch install 8-19-09 Portable Generator being connected DEQ Approval Rec |
| R7587 | Manager:Sheri Harper FC-1035,1045,1055-RENOVATE |
Status:Issued to Shop Fetzer Business Development - Renovate room 1035,1045, and 1055. | |
Active | Status Updated:20-NOV-09 99%. Wallcovering to be installed on Nov 23-25 and Nov 30-Dec 2nd. Wall Sconce installation has been added to the scope as well. |
| R8428 | Manager:Sheri Harper AUD-REPLACE CARPET/TILE |
Status:Issued to Shop Miller Auditorium - Replace carpet and tile | |
Active | Status Updated:20-NOV-09 95% Punch to be completed by Central Tile. Waiting on conifrmation that it has been completed. |
| R8872 | Manager:Sheri Harper CEAS-C213-RECONFIGURE ROOM |
Status:Issued to Shop Engineering and Applied Sciences - reconfigure room | |
Active | Status Updated:20-NOV-09 50% Construction has begun in this area. Furniture is being moved out. Surplus has been notified, painting has begun. |
| R8902 | Manager:Sheri Harper WEST HILLS-E. LOBBY-REPLACE CARPET |
Status:Issued to Shop West Hills - replace carpet | |
Active | Status Updated:20-NOV-09 50% Bid was awarded to Johnson Carpet One. Scheduled install date is November 16. This is a slip of a week due to our carpet not passing quality control at the Milliken facility. |
| R8424 | Manager:Mike Hodgkinson CEAS-STEAM COIL AND CANVAS REPAIRS |
Status:Issued to Shop Engineering and Applied Sciences - Various steam coil and canvas isolator repairs. | |
Active | Status Updated:02-NOV-09 70% done, set up time to do this with outside vendor over the week of December 17-21st Canvas repair complete. Pricing in to repair AHU 3 vibration issues. If all options fail the total cost will be 50K. MEH 6/15/09 Purchase req and AFSCME notification filled out and submitted for approval. 6/19 MEH Meeting to be scheduled on site for next week. 7/10 MEH AMS to start work 7/30 MEH AHU 3 waiting for advicve from engineer of record, work proceeding on AHU-5. MEH Duct Mods underway this week. |
| R8493 | Manager:Mike Hodgkinson CONTINOUS COMMISSIONING |
Status:Issued to Shop Physical Plant - continuous facilities monitoring for labor efficiency | |
Active | Status Updated:14-OCT-09 50% - initial project planning, 2/5/08. Progress good on AHU runtime reports, substantially complete on 2/19/2009. Progress updates from KD on 5/12/2009 shows less than 6 months payback expected ROI. MEH 5/8/2009 meeting for OA control yeilded a plan for action, $10,000 in additional funding needed. 6/1/2009. 50% done Followup and kickoff meeting tentatively scheduled for 7/10/09 MEH On Hold til Sept 14, Havel schedule filled.Mike on vacation.
MEH |
| R8569 | Manager:George Jarvis PP-BOILER #10 |
Status:Issued to Shop Beam Power Plant - boiler #10 | |
Active | Status Updated:29-MAY-09 Continue efforts toward resolving boiler transit accident; C&B walks down breeching and generates punchlist for W. Soule to address; Kasten begins insulation of breeching; WMU staff continues air and drain line installation completes breeching and insulation begun; C&B 0% |
| R9038 | Manager:Julie Lenczycki ELS-1344-CLEAN/NEW SEATING |
Status:Issued to Shop Ellsworth Hall - Clean and re-skin panels, new seating | |
Active | Status Updated:28-OCT-09 90% complete - parts are here; met with trades on 10/27 to explain scope. They will complete this the week of November 2 |
| R8717 | Manager:Conn Macomber ARCADIA CREEK STORM WATER |
Status:Issued to Shop Storm - | |
Active | Status Updated:01-JUL-09 16% Designb and contractor walk through complete. Post-bid and Pre-construction meetingheld and PO issued to |
| R8546 | Manager:Joe Odehnal SS-RES. HALLS-ASBESTOS INSPECTION |
Status:Issued to Shop Faunce Student Services - Asbestos inspection for res. halls | |
Active | Status Updated:17-NOV-09 91% Kasten Insulation is installing the piping insulation. |
| R8936 | Manager:Joe Odehnal UCC-2031-CONSTRUCT WALL |
Status:Issued to Shop University Computing Center - construct a wall | |
Active | Status Updated:17-NOV-09 51% Painting is complete. Cove base installation is being scheduled. |
| R8984 | Manager:Joe Odehnal MOORE-3060/3045-CARPET AND PAINT DOORS |
Status:Issued to Shop Moore Hall - | |
Active | Status Updated:17-NOV-09 52% New funding has been approved for painting & new carpet. |
| R9017 | Manager:Joe Odehnal LAWSON-ABATE MOLD |
Status:Issued to Shop Lawson Ice Arena - abate mold in high humidity areas. | |
Active | Status Updated:17-NOV-09 90% A meeting with Van Dam & Kruisinga is scheduled for 11-20-09. |
| R9084 | Manager:Joe Odehnal HAE-2025-INSTALL 3-4 OUTLETS |
Status:Issued to Shop Haenicke Hall - | |
Active | Status Updated:17-NOV-09 20% |
| R8697 | Manager:Eleonora Philopoulos BC-MAIN ENTRYWAY- REPLACE CARPET |
Status:Issued to Shop Bernhard Center - replace carpet | |
Active | Status Updated:21-NOV-09 80% Phone Booth installation in Lower Level is in progress. Window treatment has been ordered for the main stairwell which includes motorized and solar sensored functions. |
| R9015 | Manager:Anand Sankey VAR ENERGY CONSERVATION UPGRADES |
Status:Issued to Shop Electrical - Deferred maintenance - Round #2 - $100K.
T12 to T8 conversion upgrades.
| |
Active | Status Updated:10-NOV-09 30% EWB T12-T8 conversion |
| R8839 | Manager:Shannon Sauer-Becker CAMPUS-MASS NOTIFICATION SYSTEM |
Status:Issued to Shop - Phase 1 - Mass notification upgrade existing fire alarm system to provice voice notification alarm to 30 buildings utilizing existing audible alarms.
Phase 2 - Install exterior speakers at Welborn printing, Seibert Administration, SRC, and Seelye Athletic Center to provide exterior coverage for the mass notification project. | |
Active | Status Updated:16-NOV-09 55% Phase 1 - completed
Phase 2 - Equipment on order to provide exterior speakers for Seibert Administration, Seelye Athletic Center, Welborn Printing. |
| R8890 | Manager:Shannon Sauer-Becker UCC-(STUDY) COOLING SYSTEM |
Status:Issued to Shop University Computing Center - Perform study of cooling system. | |
Active | Status Updated:18-NOV-09 100% Recommendation presented to Sr. Management 11/13/09. Follow up meeting scheduled for 12/8 with V.P Gilchrist - project implementation and sequencing of proposed upgrades to be reviewed. |
| R9005 | Manager:Shannon Sauer-Becker FIRE ALARM SYSTEMS 2009-2010 |
Status:Issued to Shop Fire Suppression - Inspection and repair of fire alarm systems | |
Active | Status Updated:18-NOV-09 50% on going maintenance and repair. BattleCreek Aviation Facility Panel replacement. Existing panel damaged by lighting, not able to repair. New panel on order. |
| R9048 | Manager:Shannon Sauer-Becker FIRE ALARM MONITORING UPGRADE |
Status:Issued to Shop Public Safety (511 Monroe) - replace the existing fire monitoring system | |
Active | Status Updated:16-NOV-09 75% - Material on order for the relays to monitor Trimpe, Moore Hall, Ellsworth, East Hall, Sprau Tower, McCraken. Instalaltion of Cat 6 wiring to the fire alarm panles to scheduled week of 11/16. Final connections of panels to be coordinated weeko of 11/23. |
| R8750 | Manager:George Wilson SCH-REPLACE AHU3, RTU 1-4 DRIVES |
Status:Issued to Shop Electrical - Replace old drives | |
Active | Status Updated:09-NOV-09 50% Drives are here, need to be installed. |
| R9059 | Manager: FOOTBALL SUPPORT 2009 |
Status:Issued to Shop Waldo Stadium Field - | |
Active | Status Updated:27-OCT-09 80% Ongoing for the football season |
| R9083 | Manager: CHEM-TRACK COSTS FOR SPRINKLER WATER DAMAGE |
Status:Issued to Shop Chemistry Building - Track costs incurred with sprinkler inciident water damage . | |
Active | Status Updated:10-NOV-09 90% Complete with restoration |
| R9088 | Manager: SS-SEITA-Remove two walls, paint, add ceiling and fixtures |
Status:Issued to Shop Faunce Student Services - | |
Active | Status Updated:17-NOV-09 20% Room painting is in process.. |