Please frequent this page for the latest information regarding the pedestrian mall project. There are 6 contsruction phases planned. Learn more by visiting the link for each phase, located below.
The date ranges for these phases are weather dependent.
Phase 1 26 August 2011 - 1 March 2012
Phase 2 2 March 2012 - 11 March 2012
Phase 3 12 March 2012 - 29 April 2012
Phase 4 30 April 2012 - 13 May 2012
Phase 5 14 May 2012 - 24 August 2012
Phase 6 4 September 2012 - 1 May 2013

There are many related construction and planning projects that must be done in conjunction with the construction project for the new Sangren Hall. These projects vary in size and type, and may occur before, during, or even after the Sangren Hall building construction, but all fall under the category of "site work".
Projects that are related to the site around the new building:
Projects that must be accomplished prior to the start of construction:
An additional project is the expansion of the Schneider Hall chiller plant. The university has developed regional chiller plants on campus, each feeding multiple building to optimize efficiency of operation and maintenance. The chiller plant expansion will provide the additional capacity needed to supply chilled water to the new Sangren Hall facility, and to other adjacent buildings.